BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION
  • Home
  • Project Archive
  • FAQs
  • More
    • Home
    • Project Archive
    • FAQs
  • Sign In
  • Create Account

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION

Signed in as:

filler@godaddy.com

  • Home
  • Project Archive
  • FAQs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

City of Brookings 20th St S Shared Use Path

Project Details/Updates

PROJECT UPDATES

October 20, 2025 | Main Avenue South to 22nd Avenue South

  • The contractor has completed all mainline sidewalk concrete work from Main Avenue South through Branch Creek Drive.
  • Curb ramps at the Main Avenue/20th Street intersection remain to be completed. Crews are waiting to grind the existing curb before pouring the new ramps.
  • Two crossing tie-ins will be poured at the same time as the curb ramps.
  • All driveways have been poured. Cones will remain in place for a few days to allow for proper curing.
  • Striping work at the Medary Avenue/20th Street intersection will be completed this week.
  • Removal work is complete from Branch Creek Drive to 22nd Avenue South, and base course preparation is nearly finished. The contractor plans to begin sidewalk installation in this area by mid week, progressing eastward in short segments.
  • Topsoil placement, seeding, and general cleanup will continue over the coming weeks as final restoration work is completed.


October 3rd, 2025 | Branch Creek Drive to 22nd Avenue South

  • The Contractor has started removal work at Branch Creek Drive and will continue East until they reach 22nd Avenue South.
  • Sidewalk installation will occur behind the removal and base course preparation work, being completed in block-by-block segments. 
  • Concrete for driveways and curb ramps will be formed and installed by hand after all the mainline sidewalk is installed with a machine.
  • Pedestrian access along the south boulevard of 20th Street South within the construction area will be unavailable during this time.
  • Minor traffic impacts are expected on 20th Street as materials are removed from and delivered to the site.
  • Business and Private Property access will remain open, though driveways may be narrowed or shifted to temporary locations while new concrete is being installed. The Contractor will contact each property owner to identify access plans.


September 10th, 2025 | Main Avenue South to Branch Creek Drive

  • The Contractor has started removal work from Main Avenue South to Medary Avenue.
  • Work will be completed in short segments, with removals and sidewalk preparation taking place followed by concrete sidewalk installation.
  • Concrete for driveways and curb ramps will be formed and installed by hand after all the mainline sidewalk is installed with a machine.
  • Pedestrian access along the south boulevard of 20th Street South within the construction area will be unavailable during this time.
  • Minor traffic impacts are expected on 20th Street as materials are removed from and delivered to the site.
  • Business access will remain open, though driveways may be narrowed or shifted to temporary locations while new concrete is being installed.


WHAT TO EXPECT MOVING FORWARD

  • Changes and disruptions in the project area: Short term (7 days or less) lane closures on Main Avenue, Medary Avenue, 20th Street South, and Tallgrass Parkway are likely at various times throughout the project. Private driveways will require short term (7 days or less) half-width closures.
  • Yard Disruption: Minor
  • Sprinkler System Disruption: Possible
  • Special Accommodations: Pedestrian access will be moved to the sidewalk along the north side of 20th Street South for the duration of the project.


Overview

Project Description:

The City will be upgrading the sidewalk on the south side of 20th Street South, from Main Avenue S to the Branch Creek development. The current 5-foot sidewalk will be replaced with an 8-foot shared-use path for both pedestrians and cyclists. Minor drainage improvements will be made near Medary Avenue, and a short on-street path—marked with barriers and striping—will connect to the Fischback Soccer Fields driveway. Curb ramps and crossings along the route will be updated to meet ADA standards. Please expect construction activity at intersecting roads and driveways.


Why the Project:

This segment has been identified as the next phase in a larger effort to provide shared-use opportunities and connectivity throughout the City of Brookings. 


Estimated Completion:

Construction period: +/- 6 weeks to be completed by November 1, 2025


Owner:

City of Brookings 


Engineer:

Banner Associates


Contractor:

TBD

Copyright © 2024 Banner Associates, Inc. - All Rights Reserved. 

Powered by

  • Home
  • Project Archive
  • FAQs

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept