BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION

Signed in as:

filler@godaddy.com

  • Home
  • Project Archive
  • FAQs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

BMU RAW & TREATED WATER PIPELINES | 20TH ST S

Project Details/Updates

Project Update September 23, 2024


Wednesday, September 25, the contractor will begin repairing areas of settlement between 22nd Ave and Tanbury Lane.

  • No full roadway closures·
    There will be temporary lane closures while the work is ongoing.
  • Safety first
    Please watch for signage and flaggers and use caution around workers and equipment.

Thank you for your patience.


Project Update June 20, 2024

The project is substantially complete and open to traffic. The Contractor will be in the area performing punch list items and final clean up. Please be aware of workers and equipment.


Project Update May 31, 2024

The Contractor has completed the mill and overlay.  Remaining work includes installing permanent pavement markings and cleanup.  The street will remain open during this work.  Please take care around workers and equipment.


Project Update May 20, 2024

The Contractor will start mill and overlay operations between Main Ave and Windermere Way on May 23, 2024.


20th St S will NOT have a full roadway closure, only temporary lane closures.

  • Signage and flaggers will be present.  Please take care around workers and equipment.
  • Through traffic should use alternate routes and avoid the construction area if possible.


2024 Initial Status:

As a result of delays during the 2023 construction season, some tasks were reserved for completion this year. These tasks include:  

  • ADA Curb Ramp upgrades on 20th St S/Eberlein, 20th St S/Oriole, and 20th St S/7th Ave intersections.
  • Asphalt Mill and Overlay on 20th St S between Windermere Way and Main Ave S.
  • Other miscellaneous work including pavement markings, seeding, sprinkler repair, and cleanup.


Full roadway closures are not anticipated, but there will be lane closures during the mill and overlay. 

Overview

Project Description:

Brookings Municipal Utilities is installing a new 20"-diameter transmission watermain on 20th St S from 22nd Ave S to the water tower on Main Ave S. The gravity sewer on 20th St S from Medary Ave to Tanbury Lane will be upsized from 8" to 10". There will also be road resurfacing (mill and overlay). 


Why the Project:

With the population of Brookings steadily rising, this watermain will help provide the water needed to support residents. It will connect to the upcoming new Water Treatment Plant. 


Estimated Completion:

2024


Owner:

Brookings Municipal Utilities


Engineer:

Banner Associates, Inc. 


Contractor:

Winter Contracting, LLC

Copyright © 2024 Banner Associates, Inc. - All Rights Reserved. 

Powered by

  • Home
  • Project Archive
  • FAQs

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept