BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION
  • Home
  • Project Archive
  • FAQs
  • More
    • Home
    • Project Archive
    • FAQs
  • Sign In
  • Create Account

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION

Signed in as:

filler@godaddy.com

  • Home
  • Project Archive
  • FAQs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

City of Brookings 2025 Chip/Slurry Seal Projects

Project Details/Updates

WHAT TO EXPECT MOVING FORWARD

Residents and visitors in the area should watch for temporary signs posted in the boulevards indicating “No Parking”.


PROJECT UPDATES

Project Updates will be posted as they happen.


Overview

Project Description:

Various roadways within the City of Brookings will be refinished with a chip or slurry seal surface. 


Why the Project:

This chip/slurry seal work is part of standard maintenance procedures to ensure road surfaces are kept in working order. 


Estimated Completion:

Completion varies by the roadway. All segments are planned for completion by November 2025.


Owner:

City of Brookings 


Engineer:

City Engineers Office

Department of Public Works 605.692.6629


Contractor:

TBD

Copyright © 2024 Banner Associates, Inc. - All Rights Reserved. 

Powered by

  • Home
  • Project Archive
  • FAQs

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept