BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION
  • Home
  • Project Archive
  • FAQs
  • More
    • Home
    • Project Archive
    • FAQs
  • Sign In
  • Create Account

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION

Signed in as:

filler@godaddy.com

  • Home
  • Project Archive
  • FAQs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

City of Brookings 2025 Chip/Slurry Seal Projects

Project Details/Updates

WHAT TO EXPECT MOVING FORWARD

Residents and visitors in the area should watch for temporary signs posted in the boulevards indicating “No Parking”.


PROJECT UPDATES


Project Update June 18, 2025

  •  The chip/slurry is now complete
  • Please note that line-painting will be continuing over the next week on these streets
  • Please use caution when driving through these areas


Project Update June 5, 2025

  The City of Brookings is beginning its annual slurry seal/chip seal project starting Monday, June 9, 2025, weather permitting.


What is Happening?
Slurry seal is a protective street surface treatment designed to extend pavement life. This year’s application uses an improved formula to enhance durability. Work is expected to take approximately 6 working days.


Where is the Work Taking Place?

Please refer to the project map to see which streets are included. Streets will be temporarily closed during application.


 Schedule Details
• Downtown and 8th St S: Work occurs at night (Mon–Wed)
• All other areas: Work occurs during the day
• Once sealed, roads will reopen as soon as the surface sets
• Line painting will follow within two weeks of road reopening


Parking & Traffic Impact
• “No Parking” signs will be placed in advance—do not park in work zones when signs are posted
• Traffic delays should be expected
• Flaggers will assist drivers at the ends of each block
• Access to private property and boulevards will remain unaffected


 Reminders
• Follow posted signs and plan alternate routes if possible
• Your cooperation helps ensure safety and efficiency


Thank you for your patience and support as we work to maintain our city streets!


Overview

Project Description:

Various roadways within the City of Brookings will be refinished with a chip or slurry seal surface. 


Why the Project:

This chip/slurry seal work is part of standard maintenance procedures to ensure road surfaces are kept in working order. 


Estimated Completion:

Completion varies by the roadway. All segments are planned for completion by November 2025.


Owner:

City of Brookings 


Engineer:

City Engineers Office

Department of Public Works 605.692.6629


Contractor:

TBD

Copyright © 2024 Banner Associates, Inc. - All Rights Reserved. 