BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION
  • Home
  • Project Archive
  • FAQs
  • More
    • Home
    • Project Archive
    • FAQs
  • Sign In
  • Create Account

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION

Signed in as:

filler@godaddy.com

  • Home
  • Project Archive
  • FAQs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

City of Brookings 2025 Overlay Projects

Project Details/Updates

WHAT TO EXPECT MOVING FORWARD

  

Changes and disruptions in the project area:

  • The highlighted areas on the map above will be closed in segments. Detour routes will be posted whenever possible: due to multiple variables as the work progresses, detour routes may change faster than this page updates. The Contractor will attempt to provide ongoing guidance in the neighborhoods in which they are working. 
  • Temporary utility disruptions may occur in locations where utilities are being replaced. BMU will coordinate with landowners when disruptions are anticipated.
  • Temporary mailboxes may be used for portions of this project.
  • Temporary garbage collection locations may be used for portions of this project. Specific information on this will be provided as needed. 
  • Private property should not be affected. Boulevards alongside the project area may require minor grading work and will be reseeded after the project is finished. 
  • After the Contractor has arrived, homeowners should mark their lawn irrigation systems or inform the Contractor or Engineer of their locations, if known. The City will repair damaged sprinkler heads and lines upon completion of the project. 


PROJECT UPDATES


June 9, 2025 

  

7th Avenue

  • Utility installation work will continue within the full roadway closure section of 7th Avenue from 5th Street South to a location approximately 350’ south of 5th Street South.
  • In approximately one (1) week, the Contractor will extend the closure to 8th Street South to remove the asphalt surfacing and small segments of curb and gutter in preparation for the installation of new surfacing along the entire stretch.
  • Additional information will be provided prior to the extended closure.

17th Avenue

  • The week of June 9th, 2025, the Contractor will continue removing segments of curb and gutter as well as sidewalk ramps for replacement along 17th Avenue from 20th Street South to 8th Street South. The work will not require a consistent full roadway closure, but motorists are asked to be cautious of workers and equipment in the area.
  •  Intersection legs may be closed for short periods to allow for the concrete to properly cure.
  • Additional information will be provided prior to the intersection leg closures.

Deer Lane and Ridge Drive

  • The week of June 9th, 2025, the Contractor will begin milling 2” of asphalt surfacing material on Deer Lane from Thunder Pass to Dakota Trail and on Ridge Drive from Victory Street through the cul-de-sac. The milling work will be followed up by overlay paving to be completed the same week.
  • The roadways will be open to traffic while work is being completed. Motorists should expect short delays if personnel or equipment need to block the roadway, and residents in the area should expect potential short delays accessing their property to allow for proper curing time for the newly installed asphalt pavement.

3rd Avenue

  • The week of June 9th, 2025, the Contractor will set up traffic control for a full roadway closure on 3rd Avenue between Harvey Dunn Street and 11th Street. The Contractor will begin removals of the asphalt surfacing and continue with water and sanitary sewer utility replacements.
  • Placement of trash and recycling receptacles shall follow the layout shown with this project update.
  • The closure is anticipated to last 60 calendar days.

3rd Avenue, 2nd Avenue, 1st Avenue & 9th Street

  • The week of June 9th, 2025, the Contractor will begin milling 2” of asphalt surfacing material on the roadway within the respective limits shown on the map. 
  • The roadways will be open to traffic while work is being completed. Motorists should expect short delays if personnel or equipment need to block the roadway, and residents in the area should expect potential short delays accessing their property to allow for proper curing time for the newly installed asphalt pavement.


May 28, 2025 

  • 7th Avenue
    • On May 28th, 2025, the Contractor will be setting up traffic control for a full roadway closure on 7th Avenue from 5th Street South to a location approximately 350’ south of 5th Street South. The Contractor will begin removals of the asphalt surfacing and continue with water and sanitary sewer utility replacements.
    • In approximate  
  • 17th Avenue
    • The week of June 2nd, 2025, the Contractor will begin removing segments of curb and gutter as well as sidewalk ramps for replacement along 17th Avenue from 20th Street South to 8th Street South. The work will not require a consistent full roadway closure, but motorists are asked to be cautious of workers and equipment in the area.
    • Intersection legs may be closed for short periods to allow for the concrete to properly cure.
    • Additional information will be provided prior to the intersection leg closures.
  • Deer Lane and Ridge Drive
    • The week of June 2nd, 2025, the Contractor will begin milling 2” of asphalt surfacing material on Deer Lane from Thunder Pass to Dakota Trail and on Ridge Drive from Victor Street through the cul-de-sac. The milling work will be followed up by overlay paving to be completed the same week.
    • The roadways will be open to traffic while work is being completed. Motorists should expect short delays if personnel or equipment need to block the roadway, and residents in the area should expect potential short delays accessing their property to allow for proper curing time for the newly installed asphalt pavement.
  • 3rd Avenue
    • The week of June 9th, 2025, the Contractor will set up traffic control for a full roadway closure on 3rd Avenue between Harvey Dunn Street and 11th Street. The Contractor will begin removals of the asphalt surfacing and continue with water and sanitary sewer utility replacements.
    • Additional information will be provided to the residents in the area regarding access, garbage, and mail delivery. The closure is anticipated to last 60 calendar days.


April 2025

The project was bid April 15, 2025, and awarded to Bowes Construction, Inc. of Brookings. Additional information will be posted when available. 

Overview

Project Description:

Various road surfaces throughout the city will be refinished. This project includes work on select sidewalk ramps and sidewalks.

BMU is also replacing sanitary sewer and water distribution utilities on portions of the project including 7th Avenue and 3rd Avenue. 


Why the Project:

This resurfacing project ensures roads around the community are regularly maintained. The City surveys the condition of every street in the community to determine which streets need to be resurfaced each year.


The City of Brookings coordinates with BMU their planned street improvement projects. If utility replacements are needed under planned street improvements, the City and BMU work together to combine their projects into one to minimize disruptions to homeowners and the traveling public.


Estimated Completion:

Completion varies by the roadway. All segments are planned for completion by November 2025.


Owner:

City of Brookings 


Engineer:

City Engineers Office

Department of Public Works 605.692.6629


Contractor:

Bowes Construction, Inc.

Copyright © 2024 Banner Associates, Inc. - All Rights Reserved. 

Powered by

  • Home
  • Project Archive
  • FAQs

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept