BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION
  • Home
  • Project Archive
  • FAQs
  • More
    • Home
    • Project Archive
    • FAQs
  • Sign In
  • Create Account

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

BROOKINGS SD COMMUNITY CONSTRUCTION

BROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTIONBROOKINGS SD COMMUNITY CONSTRUCTION

Signed in as:

filler@godaddy.com

  • Home
  • Project Archive
  • FAQs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

BROOKINGS MILL & OVERLAY PROJECT 2023

Project Details/Updates

Project Updates September 25, 2023

  • Dacotah Bank Center Parking Lot: 
    • Complete
  • South Ridge Drive Storm Sewer
    • Complete
  • Harvey Dunn St.
    • Utility work completed
    • Project scheduled for completion early October
  • Deer Pass
    • Completed
  • Cardinal Dr/Cardinal Dr. Circle/Remington Dr
    • Scheduled for completion Mid-October
  • 9th St M&O
    • End of September to Mid-October
  • Alley between 3rd St and 4th St
    • Complete
  • Crystal Ridge Circle
    • Complete
  • Calumet
    • End of September to Mid-October
  • Teton Lane
    • Complete 
  • 4th St S Alley Inlets
    • Late September - Early October 
  • Alley Inlets between 3rd Ave and Main Ave
    • Late September - Early October 


Project Updates September 8, 2023

  • Dacotah Bank Center Parking Lot: 
    • Complete
  • South Ridge Drive Storm Sewer
    • Complete
  • Harvey Dunn St.
    • Utility work completed
    • Project scheduled for completion end of September
  • Deer Pass
    • Completed
  • Cardinal Dr/Cardinal Dr. Circle/Remington Dr
    • Scheduled for completion Mid-October
  • 9th St M&O
    • Mid-September to Mid-October
  • Alley between 3rd St and 4th St
    • Complete
  • Crystal Ridge Circle
    • Complete
  • Calumet
    • Mid-September to Mid-October
  • Teton Lane
    • Complete 


August 2, 2023:

  • The milling of the following streets will begin August 3, 2023: Crystal Ridge Circle, Teton Lane, and Deer Pass.
  • The milling work will continue until August 8, 2023.  Following, the roads will be paved and completed within 2 weeks from the start date of August 3rd.
  • Trash and recycling will not be impacted at this time.
  • Parking on the street will be prohibited. 


July 28, 2023:

 KEY TIMEFRAMES/SCHEDULES: 

COMPLETED

· Dacotah Bank Center (formerly Swiftel Center) Parking Lot: Completed

· South Ridge Drive Storm Sewer: Completed

IN PROCESS OR STARTING

· Harvey Dunn St: 7/5/23 to end of August

· Cardinal Dr / Cardinal Dr Circle / Remington Dr: Mid-August to end of September

· 9th St M&O: End of August to Mid-September

· Alley between 3rd St and 4th St: 8/2/23 to mid-August (Please see map above for trash/recycling cart placement) 

· Crystal Ridge Circle: Mid-August to Early September

· Calumet: Mid-August to Early September

· Teton Lane: Mid-August to Early September


June 29, 2023:

Harvey Dunn St will be closed from 3rd Ave to Main Ave for an estimated six weeks starting July 5, 2023. 

  • This is a complete closure: residents in the project area will not have access to their driveways. Alternative parking arrangements are shown on the map. 
  • Phase 1 includes work on sanitary sewer, water main, and storm sewer. 


June 23, 2023:

Various roadways throughout Brookings will be resurfaced this construction season. Some locations in this project will also include improvements to curb ramps, storm sewers, watermains, and sanitary sewers. The project work areas are indicated on the map above. 


What to expect moving forward:

Residents and visitors in the project area should watch for signs posted by the construction contractor. The signs will indicate upcoming road closures and detours. 


Changes and disruptions in the project area:

  • The highlighted areas on the map above will be closed in segments. Detour routes will be posted whenever possible: due to multiple variables as the work progresses, detour routes may change faster than this page updates. The Contractor will attempt to provide ongoing guidance in the neighborhoods in which they are working. 
  • Temporary mailboxes may be used for portions of this project.
  • Temporary garbage collection locations may be used for portions of this project. Specific information on this will be provided as needed. 
  • Private property should not be affected. Boulevards alongside the project area may require minor grade work and will be reseeded after the project is finished. 
  • After the Contractor has arrived, homeowners should mark their lawn irrigation systems or inform the Contractor or Engineer of their locations, if known. The City will repair damaged sprinkler heads and lines upon completion of the project.  


Key timeframes/schedule: 

  • Swiftel Center Parking Lot: Completed
  • South Ridge Drive Storm Sewer: 6/19/23 to 6/30/23
  • Harvey Dunn St: 7/5/23 to mid August
  • Cardinal Dr / Cardinal Dr Circle / Remington Dr / Deer Pass: Early August to Mid Sept.
  • 9th St M&O: Mid August to Mid September
  • Alley between 3rd St and 4th St: Early September
  • Crystal Ridge Circle: Mid August to Early September
  • Calumet: Mid August to Early September
  • Teton Lane: Mid August to Early September


Overview

Project Description:

Various road surfaces throughout the city will be refinished. This project also includes work on storm sewer, water, and sanitary sewer. 


Why the Project:

This resurfacing project ensures roads around the community are regularly maintained. The City surveys the condition of every street in the community to determine which streets need to be resurfaced each year.


Estimated Completion:

Completion varies by the roadway / storm sewer. All segments are planned for completion by November 2023.


Owner:

City of Brookings 

City Engineers Office

Department of Public Works

605.697.6629


Engineer:

Multiple engineers are involved in this project.  

  • Remington Circle, Remington Drive, Cardinal Drive, and Deer Pass
    • Jason Petersen, CDI
      605.696.3200
      jpetersen@civildes.com
  • All other segments
    • City of Brookings
      City Engineers Office
      Department of Public Works
      605.692.6629
  • Water and sanitary sewer
    • Chad Bachman
      Brookings Municipal Utilities
      605.697.8415
      cbachman@swiftel-bmu.com


Contractor:

  

  • General Contractor
    • Bowes Construction, Inc.
      605.693.3557
  • Concrete Subcontractor
    • Clark Drew Construction
      605.692.9063
  • Utility Subcontractor
    • Winter Contracting, LLC
      605.692.1881

Copyright © 2024 Banner Associates, Inc. - All Rights Reserved. 

Powered by

  • Home
  • Project Archive
  • FAQs

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept