Project Updates September 25, 2023
Project Updates September 8, 2023
August 2, 2023:
July 28, 2023:
KEY TIMEFRAMES/SCHEDULES:
COMPLETED
· Dacotah Bank Center (formerly Swiftel Center) Parking Lot: Completed
· South Ridge Drive Storm Sewer: Completed
IN PROCESS OR STARTING
· Harvey Dunn St: 7/5/23 to end of August
· Cardinal Dr / Cardinal Dr Circle / Remington Dr: Mid-August to end of September
· 9th St M&O: End of August to Mid-September
· Alley between 3rd St and 4th St: 8/2/23 to mid-August (Please see map above for trash/recycling cart placement)
· Crystal Ridge Circle: Mid-August to Early September
· Calumet: Mid-August to Early September
· Teton Lane: Mid-August to Early September
June 29, 2023:
Harvey Dunn St will be closed from 3rd Ave to Main Ave for an estimated six weeks starting July 5, 2023.
June 23, 2023:
Various roadways throughout Brookings will be resurfaced this construction season. Some locations in this project will also include improvements to curb ramps, storm sewers, watermains, and sanitary sewers. The project work areas are indicated on the map above.
What to expect moving forward:
Residents and visitors in the project area should watch for signs posted by the construction contractor. The signs will indicate upcoming road closures and detours.
Changes and disruptions in the project area:
Key timeframes/schedule:
Project Description:
Various road surfaces throughout the city will be refinished. This project also includes work on storm sewer, water, and sanitary sewer.
Why the Project:
This resurfacing project ensures roads around the community are regularly maintained. The City surveys the condition of every street in the community to determine which streets need to be resurfaced each year.
Estimated Completion:
Completion varies by the roadway / storm sewer. All segments are planned for completion by November 2023.
Owner:
City Engineers Office
Department of Public Works
605.697.6629
Engineer:
Multiple engineers are involved in this project.
Contractor:
Copyright © 2024 Banner Associates, Inc. - All Rights Reserved.
Created and maintained by Banner Associates, Inc.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.